Multiply length × width × average depth. Add an order allowance for uneven subgrade, spillage and rounding. Bag yield is wet mixed volume from the product label. Quote truck minimums and delivery separately. Use measurements and reinforcement specified for your project.

Worked example

A 4 × 3 m slab at 100 mm needs 1.2 m³ net. Add 10% for 1.32 m³. At 12 litres per bag, order 110 bags.

Use these quantities for estimating and purchasing. Have structural design, code compliance and project details checked by a qualified professional.